SDA-MCS Based Risk Response Strategy Model for Road Construction Project

Rester S. Jinang
Volume 4 July 2023
Presented in 4th International Conference on Multidisciplinary Industry and Academic Research (ICMIAR), July 7 - 8, 2023

Abstract

The SDA-MCS Based Risk Response Strategy (RRS) Model for Road Construction Project is developed to formulate strategies in improving the current condition by analyzing the risk factors and simulating strategies. The first part of the research focused on risk evaluation by Schedule Delay Analysis method: As-planned vs As-built method. The SDA determined the commonly occurring delaying factors and its extent in the project. Risk Response Strategy matrix is used to categorize risk factors according to occurrence probability and impact to the project; and strategize. Subsequently, these strategies can be imposed to the project schedule baseline in consideration with project scope and admissibility. Monte Carlo simulation is done to generate possible critical path duration. Moreover, the simulated critical paths are tested to determine the probability of success.

Keywords: Risk Response Strategy, Delay, Schedule Delay Analysis (SDA), As-planned vs As-built method, Planned Schedule, Road Construction Project, Monte Carlo Simulation   

*This paper is presented at the 4th International Conference on Multidisciplinary Industry and Academic Research (ICMIAR) 2023

References

Ali Abbas, Zia Ud Din, Rizwan Farooqui (2016). Achieving Greater Project Success & Profitability through Pre-construction Planning: A Case-based Study, Procedia Engineering, Volume 145, Pages 804-811, ISSN 1877-7058, https://doi.org/10.1016/j.proeng.2016.04.105.

Ashtari, Mohammad Amin, Ramin Ansari, Erfan Hassannayebi, and Jaewook Jeong (2022). Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach, Buildings 12, no. 10: 1660. https://doi.org/10.3390/buildings12101660

Ashwini Arun Salunkhe, Rahul S. Patil, Sellakutty, Dinesh, Jayashree Jayakumar (2017).  Statistical Methods for Construction Delay Analysis, IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE), Volume 9, Issue 2, Pages 58-62, e-ISSN: 2278-1684,p-ISSN: 2320-334X, https://www.researchgate.net/publication/322820770

Ayman H. Al-Momani (2000).  Construction delay: a quantitative analysis, International Journal of Project Management, Volume 18, Issue 1, Pages 51-59, ISSN 0263-7863, https://doi.org/10.1016/S0263-7863(98)00060-X.

C.B. Alexandre, J. Salguero, M.E. Peralta, F. Aguayo, E. Ares (2017). New design and manufacturing technologies for craft products, Procedia Manufacturing, Volume 13, Pages 1284-1291, ISSN 2351-9789, https://doi.org/10.1016/j.promfg.2017.09.054.

Espinosa-Garza, I. Loera-Hernández, N. Antonyan (2017). Increase of productivity through the study of work activities in the construction sector, Procedia Manufacturing, Volume 13, Pages 1003-1010, ISSN 2351-9789, https://doi.org/10.1016/j.promfg.2017.09.100.

Gyamfi, Timothy Adu, Humphrey Danso (2018). Schedule Delay Analysis of Construction Projects in Ghana: Objectives, Importance and Effects

Jeong, Joo-Seong, & Jung, Eun-Young. (2017). Construction Delays in Developing Countries: A Review. Journal of Construction Engineering and Project Management, 7(1), 1–12. https://doi.org/10.6106/JCEPM.2017.3.30.001

Kazar, G., Mutlu, U. and Tokdemir, O.B. (2022), “Development of zero-based budgeting approach for multinational construction contractors”, Engineering, Construction and Architectural Management, https://doi.org/10.1108/ECAM-05-2022-0408

Kirk D. Gothand (2003). Schedule delay analysis: Modified Windows approach, Cost Engineering; Morgantown Vol. 45, Iss. 9, https://www.proquest.com/openview/ca417487ce8d5fe6e9348434fba388f4/1?pq-origsite=gscholar&cbl=49080

Laura Florez, Jean C. Cortissoz (2017). Using Workers Compatibility to Predict Labor Productivity through Cluster Analysis, Procedia Engineering, Volume 196,, Pages 359-365, ISSN 1877-7058, https://doi.org/10.1016/j.proeng.2017.07.211.

Montemar, Louie C. (January 10, 2018). Thinking Beyond Politics: The 2018 National Budget, Infrastructure, and Economic Growth, Retrieve from https://www.bworldonline.com/2018-national-budget-infrastructure-economic-growth/

Nagata, Mark F., PSP, CDT, William A. Manginelli, J. Scott Lowe, P.E., CDT, Theodore J. Trauner, P.E. (2018). Construction Delays (Third Edition), Pages 73–82, Chapter Four – Types of Construction Delay: Retrieve from https://www.sciencedirect.com/science/article/pii/B9780128112441000045

Paul Asabre Pinamang, Timothy Adu Gyamfi, Humphrey Danso, Joshua Ampofo Kwame (2018). Schedule Delay Analysis of Construction Projects in Ghana: Objectives, Importance and Effects, Civil and Environmental Research, Vol.10, No.4, ISSN 2225-0514, www.iiste.org

Pier Luigi Guida, Giovanni Sacco (2019). A method for project schedule delay analysis, Computers & Industrial Engineering, Volume 128, Pages 346-357, ISSN 0360-8352, https://doi.org/10.1016/j.cie.2018.12.046.

Richard C. Thompson, Yi Su, Gunnar Lucko (2017). Measuring Project Performance Inspired by Stock Index, Procedia Engineering, Volume 196, Pages 706-713, ISSN 1877-7058, https://doi.org/10.1016/j.proeng.2017.07.237.

Roumeissa, S., Karima, M., & Souad, S. B. (2022). Prediction of Delays in Construction Projects in Algeria. European Journal of Formal Sciences and Engineering, 5(1), 73–79. https://doi.org/10.26417/ejfe.v1i1.p6-10

Roumeissa, S., Karima, M., & Souad, S. B. (2022). Prediction of Delays in Construction Projects in Algeria. European Journal of Formal Sciences and Engineering, 5(1), 73–79. https://doi.org/10.26417/ejfe.v1i1.p6-10

SHI Zhou, JI Feng, YU Wanqing, WEI Qingdong. Dynamic Risk Assessment of Large Bridge Construction[J].同济大学学报(自然科学版),2021,49(5):634~642

Shou Qing Wang, Mohammed Fadhil Dulaimi & Muhammad Yousuf Aguria (2004) Risk management framework for construction projects in developing countries, Construction Management and Economics, 22:3, 237-252, DOI: 10.1080/0144619032000124689, https://doi.org/10.1080/0144619032000124689

Trauner, Ted, 2009, Construction Delays, 2nd Edition, ISBN: 9781856176774, eBook ISBN: 9780080957142, Retrieved from Elsevier Inc.knovel.com

Woldesenbet, Asregedew, “David” Hyung Seok Jeong, and Garold D. Oberlender (2012). Estimation for Highway Projects, Retrieve from https://www.researchgate.net/publication/278405900

Zetta R. Kamandang, Jyh-Bin Yang, and Indradi Wijatmiko (2017). An Empirical Study on Analyzing Schedule Delays of Construction Project in Indonesia, 34th International Symposium on Automation and Robotics in Construction (ISARC 2017), https://www.researchgate.net/publication/320294186

Cite this article:

Jinang, R.S. (2023). SDA-MCS Based Risk Response Strategy Model for Road Construction Project. Industry and Academic Research Review, 4 (1), 420-425.

License:

TRP Cover Page
The Research Probe

Proceedings journal for institutional researches.

MEIR COVER Page
Management, Education & Innovation Review

Proceedings journal for ICMEI.

ISRC Cover Page
International Student Research Review

Proceedings journal for ISRC.

Scroll to Top