SDA-MCS Based Risk Response Strategy Model for Road Construction Project
Rester S. Jinang
Abstract
The SDA-MCS Based Risk Response Strategy (RRS) Model for Road Construction Project is developed to formulate strategies in improving the current condition by analyzing the risk factors and simulating strategies. The first part of the research focused on risk evaluation by Schedule Delay Analysis method: As-planned vs As-built method. The SDA determined the commonly occurring delaying factors and its extent in the project. Risk Response Strategy matrix is used to categorize risk factors according to occurrence probability and impact to the project; and strategize. Subsequently, these strategies can be imposed to the project schedule baseline in consideration with project scope and admissibility. Monte Carlo simulation is done to generate possible critical path duration. Moreover, the simulated critical paths are tested to determine the probability of success.
Keywords
Risk Response Strategy, Delay, Schedule Delay Analysis (SDA), As-planned vs As-built method, Planned Schedule, Road Construction Project, Monte Carlo Simulation
Author information & Contribution
Disclosure statement
No potential conflict of interest was reported by the author(s).
Funding
This work was not supported by any funding.
AI Declaration
Notes
This paper is presented in 4th International Conference on Multidisciplinary Industry and Academic Research (ICMIAR)
Acknowledgement
References
Ali Abbas, Zia Ud Din, Rizwan Farooqui (2016). Achieving Greater Project Success & Profitability through Pre-construction Planning: A Case-based Study, Procedia Engineering, Volume 145, Pages 804-811, ISSN 1877-7058, https://doi.org/10.1016/j.proeng.2016.04.105.
Ashtari, Mohammad Amin, Ramin Ansari, Erfan Hassannayebi, and Jaewook Jeong (2022). Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach, Buildings 12, no. 10: 1660. https://doi.org/10.3390/buildings12101660
Ashwini Arun Salunkhe, Rahul S. Patil, Sellakutty, Dinesh, Jayashree Jayakumar (2017). Statistical Methods for Construction Delay Analysis, IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE), Volume 9, Issue 2, Pages 58-62, e-ISSN: 2278-1684,p-ISSN: 2320-334X, https://www.researchgate.net/publication/322820770
Ayman H. Al-Momani (2000). Construction delay: a quantitative analysis, International Journal of Project Management, Volume 18, Issue 1, Pages 51-59, ISSN 0263-7863, https://doi.org/10.1016/S0263-7863(98)00060-X.
C.B. Alexandre, J. Salguero, M.E. Peralta, F. Aguayo, E. Ares (2017). New design and manufacturing technologies for craft products, Procedia Manufacturing, Volume 13, Pages 1284-1291, ISSN 2351-9789, https://doi.org/10.1016/j.promfg.2017.09.054.
Espinosa-Garza, I. Loera-Hernández, N. Antonyan (2017). Increase of productivity through the study of work activities in the construction sector, Procedia Manufacturing, Volume 13, Pages 1003-1010, ISSN 2351-9789, https://doi.org/10.1016/j.promfg.2017.09.100.
Gyamfi, Timothy Adu, Humphrey Danso (2018). Schedule Delay Analysis of Construction Projects in Ghana: Objectives, Importance and Effects
Jeong, Joo-Seong, & Jung, Eun-Young. (2017). Construction Delays in Developing Countries: A Review. Journal of Construction Engineering and Project Management, 7(1), 1–12. https://doi.org/10.6106/JCEPM.2017.3.30.001
Kazar, G., Mutlu, U. and Tokdemir, O.B. (2022), “Development of zero-based budgeting approach for multinational construction contractors”, Engineering, Construction and Architectural Management, https://doi.org/10.1108/ECAM-05-2022-0408
Kirk D. Gothand (2003). Schedule delay analysis: Modified Windows approach, Cost Engineering; Morgantown Vol. 45, Iss. 9, https://www.proquest.com/openview/ca417487ce8d5fe6e9348434fba388f4/1?pq-origsite=gscholar&cbl=49080
Laura Florez, Jean C. Cortissoz (2017). Using Workers Compatibility to Predict Labor Productivity through Cluster Analysis, Procedia Engineering, Volume 196,, Pages 359-365, ISSN 1877-7058, https://doi.org/10.1016/j.proeng.2017.07.211.
Montemar, Louie C. (January 10, 2018). Thinking Beyond Politics: The 2018 National Budget, Infrastructure, and Economic Growth, Retrieve from https://www.bworldonline.com/2018-national-budget-infrastructure-economic-growth/
Nagata, Mark F., PSP, CDT, William A. Manginelli, J. Scott Lowe, P.E., CDT, Theodore J. Trauner, P.E. (2018). Construction Delays (Third Edition), Pages 73–82, Chapter Four – Types of Construction Delay: Retrieve from https://www.sciencedirect.com/science/article/pii/B9780128112441000045
Paul Asabre Pinamang, Timothy Adu Gyamfi, Humphrey Danso, Joshua Ampofo Kwame (2018). Schedule Delay Analysis of Construction Projects in Ghana: Objectives, Importance and Effects, Civil and Environmental Research, Vol.10, No.4, ISSN 2225-0514, www.iiste.org
Pier Luigi Guida, Giovanni Sacco (2019). A method for project schedule delay analysis, Computers & Industrial Engineering, Volume 128, Pages 346-357, ISSN 0360-8352, https://doi.org/10.1016/j.cie.2018.12.046.
Richard C. Thompson, Yi Su, Gunnar Lucko (2017). Measuring Project Performance Inspired by Stock Index, Procedia Engineering, Volume 196, Pages 706-713, ISSN 1877-7058, https://doi.org/10.1016/j.proeng.2017.07.237.
Roumeissa, S., Karima, M., & Souad, S. B. (2022). Prediction of Delays in Construction Projects in Algeria. European Journal of Formal Sciences and Engineering, 5(1), 73–79. https://doi.org/10.26417/ejfe.v1i1.p6-10
Roumeissa, S., Karima, M., & Souad, S. B. (2022). Prediction of Delays in Construction Projects in Algeria. European Journal of Formal Sciences and Engineering, 5(1), 73–79. https://doi.org/10.26417/ejfe.v1i1.p6-10
SHI Zhou, JI Feng, YU Wanqing, WEI Qingdong. Dynamic Risk Assessment of Large Bridge Construction[J].同济大学学报(自然科学版),2021,49(5):634~642
Shou Qing Wang, Mohammed Fadhil Dulaimi & Muhammad Yousuf Aguria (2004) Risk management framework for construction projects in developing countries, Construction Management and Economics, 22:3, 237-252, DOI: 10.1080/0144619032000124689, https://doi.org/10.1080/0144619032000124689
Trauner, Ted, 2009, Construction Delays, 2nd Edition, ISBN: 9781856176774, eBook ISBN: 9780080957142, Retrieved from Elsevier Inc.knovel.com
Woldesenbet, Asregedew, “David” Hyung Seok Jeong, and Garold D. Oberlender (2012). Estimation for Highway Projects, Retrieve from https://www.researchgate.net/publication/278405900
Zetta R. Kamandang, Jyh-Bin Yang, and Indradi Wijatmiko (2017). An Empirical Study on Analyzing Schedule Delays of Construction Project in Indonesia, 34th International Symposium on Automation and Robotics in Construction (ISARC 2017), https://www.researchgate.net/publication/320294186
Cite this article:
Jinang, R.S. (2023). SDA-MCS Based Risk Response Strategy Model for Road Construction Project. Industry and Academic Research Review, 1 (1), 420-425.
License:
![]()
This work is licensed under a Creative Commons Attribution (CC BY 4.0) International License.
Related articles:
Lived Experiences of Learners During Disaster: Basis in Formulating Policies on Disaster Risk Reduct...
Intrusion of Code-Switching in Exploring the Principles of Sentence and Paragraph Constructions: An ...
Factors Influencing Reading Comprehension and Difficulties Among Intermediate Learners: Basis For De...
Most read articles in this journal
- Reading Comprehension Difficulties Among Junior High School Learners
- Factors Influencing Reading Comprehension and Difficulties Among Intermediate Learners: Basis For Developing Remedial Reading Intervention
- Analysis of school rules and regulation implementation: Basis for policy enhancement program
- Technical vocational students’ higher learning institution preference and level of academic and skills preparedness
- The Lived Experiences of Young Learners Involved in Online Gaming
- Factors Affecting Reading Proficiency and Difficulties of Grade 5 Pupils: Bases for a Reading Intervention Program
- Predictors of Performance in the Certified Public Accountants’ Licensure Examination
- Pupils’ reading comprehension: Basis for the development of reading instructional material
- Student-Mother: The Dual Role in the New Normal Mode of Learning
- The Lived Experiences of Teachers and Parents on Kindergarten Learners’ Separation Anxiety